Choosing a fit-out contractor is the one decision on a project that is genuinely hard to reverse. You can change a finish, you can change a supplier, but changing the contractor halfway through means re-pricing the remaining scope, losing the warranty on what is already built, and two months nobody gives back. It is worth a week of your time, not a phone call.

What follows is not a generic checklist. These are the things we check before we let a subcontractor onto one of our own sites, and they are the same things we expect a serious client to ask us.

1. Classification and registration, before anything else

Ask for the commercial registration and the contractor classification certificate before the first meeting, not after. The classification states what categories of work the company is qualified for and the ceiling value it may contract. A company that hesitates to send those documents within one working day has answered the question.

2. Completed work of the same type, not simply a lot of work

A contractor who has delivered forty villas is not automatically the right choice for a restaurant kitchen or a cold-storage warehouse. Ask precisely: what were the last three projects of my type, when were they handed over, and who was the project manager? Then ask to visit one that has been in use for a year. A space after twelve months of trading tells you what no photograph will.

3. A priced bill of quantities, not a single number

A one-page quotation with a lump sum is a promise, not a price. A serious submission is a schedule of rates: item, unit, quantity, unit rate, total. That schedule is the only way to compare two bids fairly, and it is what protects you later, because the rate for a variation is already agreed.

Treat an unusually low bid with suspicion. In fit-out, a bid more than about 20% below the others rarely means efficiency. It usually means an omitted item, a downgraded specification, or an intention to recover the gap through variations.

4. Specifications named by product

"High-quality porcelain" is not a specification. "Porcelain 600x600, manufacturer, model, R10 slip rating" is. Any line that is not pinned to a name and a number will be interpreted in the contractor's favour on site, and you are the one who lives with the interpretation.

5. A programme tied to payments

Ask for a programme with stages and dates, then tie payments to measurable completion rather than to elapsed time. "On completion and sign-off of plastering" protects both parties. "At the end of month two" protects one.

6. The project manager, by name

The difference between a managed project and an abandoned one is a single person. Ask for the site engineer's name, how many projects they run simultaneously, how many site visits a week you should expect, and who covers their leave. Then ask for the name to appear in the contract.

7. Warranty, and what happens after handover

Ask for the warranty period on builder's work and separately on MEP. Ask whether it covers materials and labour or labour alone. Then ask a practical question: if a leak appears in four months, who do I call, and how many days until someone is on site? A company that already has an answer has had the problem before.

One warning sign that covers most of the others

If you are asked to transfer a substantial advance before a fully detailed contract is signed, stop. A reasonable advance covers site setup and first materials, and it follows the contract rather than preceding it.

We work this way because we have seen the alternative. Look at projects we have delivered, read what we cover in our services, or send us your drawings and we will come back with a bill of quantities rather than a number.